Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

A.3
B.4
C.5
D.6

Correct Answer

6

Detailed Explanation

Time taken by A, T, M to complete a job are in ratio 5:8:10 Working 8 hrs per day for 4 days, they complete the work. Let work done per hour be 1/5x, 1/8x and 1/10x => 32(1/5x + 1/8x + 1/10x) = 1 => x = 68/5 A and T work together for 6 days working 20/3 hours per day, i.e., 40 hours. Work left = 1 – 40(1/5x + 1/8x) = 1 – 13/x = 3/68 M will take (3/68)/(1/68x2) = 6 hours Correct Answer is D